WASHINGTON, Dec. 4 - For the first time in three decades, companies are getting ready to build nuclear reactors in the United States. They intend to do so under streamlined procedures meant to avoid the long delays and cost overruns that crippled the industry last time around.

But with early jockeying under way to win government approval for this new generation of plants, ominous signs are emerging that the plans may not go smoothly.

And if the industry succeeds in winning approval for as many new reactors as it wants, 31 and counting, the capacity of nuclear suppliers is likely to be strained. By most estimates, they can fabricate enough parts for only three or four reactors a year, and the United States will be competing with other countries that want to build nuclear plants.

Some of the most important parts can be cast only by a single foundry, Japan Steel Works. "The global supply chain is going to be the pacing item," Mr. Wallace said.
covelogibbs

Add your response

Login/Registration is required to add a response.